Sellafield - Inspection ID: 54134

Executive summary

Date(s) of inspection: 

August 2025

Aim of inspection

The purpose of this Inspection was to sample evidence of Sellafield Limited's (SLs) arrangements for the PD1 electrical switchboard replacement and the impact on normal operations within Analytical Services in order to inform a regulatory judgement regarding the permission for this activity to proceed. 

Subject(s) of inspection

  • Health & Safety at Work Act - Rating: Green
  • LC11 - Emergency arrangements - Rating: Green
  • LC22 - Modification or experiment on existing plant - Rating: Green
  • LC23 - Operating rules - Rating: Green
  • LC24 - Operating instructions - Rating: Green
  • LC26 - Control and supervision of operations - Rating: Green

Key findings, inspector's opinions and reasons for judgement made

This Inspection was conducted to sample evidence of Sellafield Limited's (SL's) arrangements for the PD1 electrical switchboard replacement and the impact on normal operations within Analytical Services in order to inform a regulatory judgement regarding the permission for this activity to proceed.  

Conclusion

From the evidence sampled, plant and equipment visited and conversations with the relevant Sellafield staff I am of the opinion that the B229 PD1 outage has been well planned, that appropriate preparations have been made to enable the work to proceed as planned and that independent scrutiny has been applied.  This leads me to conclude that risks are being properly controlled and that suitable contingencies are in place to reduce overall risk to as low as reasonably practicable.  I am satisfied that Sellafield Ltd is ready to commence the B229 PD1 outage as planned on 1st September 2025 and I recommend the hold point HPCP 657 is released to allow this.