Skip to content

Sellafield – Inspection ID: 50318

Executive summary

Date(s) of inspection:

  • December 2022

Aim of inspection

The aim of the inspection was to sample evidence of implementation of the Sellafield Limited arrangements for compliance with Licence Condition 15, specifically within the Combined Services, in order to inform a regulatory judgement regarding the licensee's compliance with legal duties under the nuclear site licence.

Subject(s) of inspection

  • LC15 - Periodic Review - Rating - Green

Key findings, inspector's opinions and reasons for judgement made

The Office for Nuclear Regulation undertakes all regulatory interactions with the Sellafield Limited Site Licensee against a strategy defined by the ONR Sellafield, Decommissioning, Fuel and Waste Division. The strategy requires inspections to be performed against Licence Condition 15 (LC15) “Periodic Review”, which requires the licensee to make and implement adequate arrangements for the periodic and systematic review and reassessment of safety cases. The inspection was carried out against Relevant Regulatory Guidance, including:
  • Nuclear Safety Technical Inspection Guide - LC15 Periodic Review, NS-INSP-GD-015 Revision 5
  • Nuclear Safety Technical Assessment Guide - Periodic Safety Review (PSR), NS-TAST-GD-050 Revision 8
  • IAEA Specific Safety Guide – Periodic Safety Review for Nuclear Power Plants, SSG-25
The purpose of this Inspection was for ONR to assess the adequacy of the Combined Services Periodic Safety Review (PSR) by ensuring that Sellafield Limited: has implemented its LC15 arrangements; and, is taking the necessary steps to continue to operate and maintain the plant in a manner that will ensure that risks will continue to be reduced so far as is reasonably practicable. The inspection was carried out in accordance with a plan shared with Sellafield Limited. The objectives of this inspection were to; gain confidence that Sellafield Limited has undertaken an adequate PSR, accounting for lessons learnt and future foreseeable challenges; and, establish if Sellafield Limited has credible resolution plans to implement improvements identified by the PSR. On 2 December 2022, ONR carried out an inspection of LC15 compliance relating to the Combined Services PSR. The ONR inspection team was led by the PSR project Inspector, with support from the Combined Services Site Inspector and a Nuclear Safety Inspector. The inspection involved the following activities: sampling the implementation of Sellafield Limited’s LC15 arrangements; sampling the documents produced by implementing these arrangements; and, discussions with appropriate members of Sellafield Limited staff. Based on the evidence obtained during these activities, ONR considers that Sellafield Limited has implemented its LC15 arrangements and produced an adequate PSR of the Combined Services. ONR also considers that the PSR accounts for lessons learned and foreseeable future challenges and that arrangements to address the actions identified during the PSR are adequate. Since ONR considers that Sellafield Limited has adequately implemented its arrangements for compliance with LC15, ONR judges that an inspection rating of Green (no formal action) is appropriate for compliance against LC15 (Periodic Review). This inspection identified matters related to Sellafield Limited’s LC15 arrangements, rather than to implementation of these arrangements. These will be followed up during a separate corporate LC15 inspection.

Conclusion

On the basis of the evidence sampled at the time of the inspection, we judged that Sellafield Limited has adequately implemented its arrangements for LC15 (SLP 2.17.04 “How do I Review a Safety Case?”). The Sellafield Limited teams involved in the preparation of the Combined Services PSR and with the inspection were well informed and helpful during the inspection. ONR also considers that the PSR accounts for lessons learned and foreseeable future challenges and that arrangements to address the recommendations and shortfalls identified during the PSR are adequate.  Noting the ONR guidance on inspection ratings, it is my opinion that an inspection rating of Green (no formal action) is appropriate.