Skip to content

Sellafield Site - Inspection ID: 52125

Executive summary

Date(s) of inspection:

  • February 2024

Aim of inspection

In accordance with the Office for Nuclear Regulation’s (ONR’s) Sellafield Strategy, each year ONR performs a series of planned inspections to seek assurance of compliance against selected licence conditions, targeted at those facilities with significant importance to nuclear safety. One such inspection was undertaken at   Special Nuclear Materials Value Stream (SNM) facilities at North and South within the Sellafield site in West Cumbria  to sample evidence of implementation of Sellafield Limited's arrangements for compliance with Licence Condition (LC) 28 (examination, inspection, maintenance and testing), specifically to  overpacks and Magnox hybrid  packages,  in order to inform a regulatory judgement regarding the licensee’s compliance with its legal duties under the nuclear site licence.

Subject(s) of inspection

  • LC28 - Examination, inspection, maintenance and testing - Rating: Green

Key findings, inspector's opinions and reasons for judgement made

The inspection was undertaken on 7 and 8 February 2024.  The inspection team comprised of the SNM site inspector and a structural  integrity   specialist inspector. The inspection was also attended by one nuclear graduate trainee. The inspection targeted compliance against Licence Conditions (LC)  28 (Examination, inspection, maintenance and testing), specifically in relation to overpacks and Magnox hybrid packages.
 
The inspection involved a planning phase and  a site visit, which included  discussions with relevant Sellafield Limited personnel, review of records, and sampling of information contained within electronic databases and other documentation.
 
Based on the  evidence sampled, we concluded the following:
 
No significant matters were identified that required immediate regulatory attention.
 
Sellafield Limited is currently implementing a number of improvements in response to Regulatory  Issue 11185, previously raised in this area, which will aid further clarity and transparency in demonstrating compliance with the corporate arrangements.
 
Overall, we were satisfied that   the licensee provided an adequate level of assurance and evidence to demonstrate compliance with LC28. Examination, inspection, maintenance and testing has been undertaken to satisfy both the LC28 requirements as well as other requirements identified by SNM Technical.  
 
Based on the training evidence sampled we were satisfied that the selected personnel were suitably qualified and experienced for the task and their training  was found to be in date.
 
Some minor anomalies were identified  and regulatory advice was provided.

Conclusion

On the basis of evidence sampled and the interactions that we held with Sellafield Limited staff, at the time of the inspection, we judge that, on balance, Sellafield Limited has  largely   implemented its arrangements for compliance with LC28 (Examination, inspection, maintenance and testing).  Upon consideration of the ONR guidance on inspection ratings, we judge that a rating of green (no formal action) is appropriate.