GE Healthcare Ltd - Planned inspection of LC 2

Executive summary

Purpose of Intervention

This inspection, one of a series of planned inspections for 2018/19 as described in ONR’s Decommissioning, Fuel & Waste (DFW) sub-division’s strategy, was undertaken to assess compliance with licence condition (LC) 2 – Marking of the Site Boundary at the Maynard Centre nuclear licensed site, Cardiff.

Interventions Carried Out by ONR

LC2 requires the licensee to make and implement adequate arrangements to prevent unauthorised persons from entering the site.

This intervention was carried out to assess the licensee’s arrangements against ONR’s requirements.

Explanation of Judgement if Safety System Not Judged to be Adequate

N/A

Key Findings, Inspector's Opinions and Reasons for Judgements Made

Following a review of the licensee’s LC2 arrangements against the relevant guidance I am of the opinion that they adequately meet ONR’s expectations for such arrangements.

Conclusion of Intervention

The inspection confirmed that unauthorised persons are prevented from entering the site in accordance with the licensee’s arrangements for Licence Condition 2.