Compliance with Licence Conditions 2, 8, 9 and 16 Inspection together with Projects and Safety Representative meetings

Executive summary

Purpose of intervention

This report describes an ONR intervention conducted at Magnox Ltd's Hinkley Point A nuclear licensed site, undertaken as part of a series of routine interventions set out in the Integrated Intervention Strategy document.

Interventions Carried Out by ONR

This intervention was planned to examine the adequacy of the licensee's arrangements to ensure compliance with:

In addition ONR were also provided with progress updates for the 'Ministores'; fuel element debris retrieval and ponds decommissioning projects.

Explanation of Judgement if Safety System Not Judged to be Adequate

N/A

Key Findings, Inspector's Opinions and Reasons for Judgements Made

There are no key findings.

Conclusion of Intervention

I conclude that, from the evidence presented during the intervention, that the licensee's compliance with licence conditions 2, 8, 9 and 16 is adequate.