Compliance Inspection and Joint Regulatory Project Update Meeting

Executive summary

Purpose of intervention

This report describes an inspection of Magnox Ltd's Bradwell licensed site, undertaken as part of a series of routine interventions set out in the Integrated Intervention Strategy document.

Interventions Carried Out by ONR

I carried out a planned inspection of the site arrangements for LC22 Modification or Experiment on Existing Plant. I received a progress update on the care and maintenance transition programme and attended a joint regulatory project update meeting.

Explanation of Judgement if Safety System Not Judged to be Adequate

This intervention did not include a safety system inspection.

Key Findings, Inspector's Opinions and Reasons for Judgements Made

I found Bradwell had adequate arrangements for controlling Modifications or Experiments on Existing Plant. Site was able to provide evidence that the safety requirements applicable to each plant modification are implemented at the place of work.

Conclusion of Intervention

In the areas I considered during the intervention I found that the arrangements for compliance with licence condition 22 and their implementation at Bradwell were of a good standard.