Compliance inspections for LC9, LC13 and Review of EPR Capability Map

Executive summary

Purpose of Intervention

One of a programme of planned inspections at LLWR during 2018/19.

Interventions Carried Out by ONR

I examined LLWR’s arrangements and procedures for compliance with licence conditions (LC) 9 instructions to persons on the site and LC13 nuclear safety committee.

Explanation of Judgement if Safety System Not Judged to be Adequate

Not applicable

Key Findings, Inspector's Opinions and Reasons for Judgements Made

LC Inspections: I, interviewed the LC 9 and 13 process owners and operations personnel responsible for implementing and monitoring relevant procedures (LC9) and arrangements (LC13). I inspected a sample of the key documents provided by LLWR ahead of and during this inspection. I also checked a number of supporting documents including training records and for compliance assurance procedures. Overall I found the management arrangements to be adequate in the areas sampled.

Review of Emergency Preparedness and Response Capability Map (EPRCM); I focused on LLWR’s re- assessment and implementation of specific capabilities where improvements were¬† identified in the first version issued in 2015.

Conclusion of Intervention

I did not find any shortfalls in the documented procedures for LC 9 and arrangements for LC13 and concluded these to be adequate.