Inspection of Arrangements for Compliance with: Licence Condition 19: Construction or Installation of New Plant

Executive summary

Purpose of intervention

The inspection comprised the planned inspection of implementation of the following key procedures which the NNB GenCo site functions use to manage:

The procedures form part of NNB GenCo’s arrangements for complying with Licence Condition 19: Construction or installation of new plant.

Interventions Carried Out by ONR

Inspection of NNB GenCo’s implementation of the company procedures:

Key Findings, Inspector's Opinions and Reasons for Judgements Made

Licence Condition 19 – Construction or installation of new plant.

NNB GenCo’s procedures for managing Request For Information and Field Change Requests:

The HPCSI inspection of Consolidated Change Information System concluded that NNB GenCo has demonstrated that the application of its arrangements to the Gallery Mock-Up is compliant with the procedures.

The HPCSI is seeking clarification of the role and operation of the Site Design Liaison Team.

Conclusion of Intervention

The HPSCI judges NNB GenCo implementation of its procedures for managing Requests For Information and Field Change Requests, which form part of NNB GenCo arrangements for compliance with Licence Condition 19: Construction or installation of new plant, to be GREEN.