Hinkley Point C. Planned Compliance Inspection: LC16: Site plans, designs and specifications

Executive summary

Purpose of intervention

NNB GenCo sought a meeting with ONR to:

Interventions Carried Out by ONR

Attended a scheduled level 4 meeting with the Head of Owner Engineering, owner of the arrangements for compliance with LC16. The meeting was attended by NNB GenCo personnel representing Owners Engineering Integration Branch, Design Authority Safety Case Branch, Site Controls and Planning.

Explanation of Judgement if Safety System Not Judged to be Adequate

Not applicable.

Key Findings, Inspector's Opinions and Reasons for Judgements Made

The Hinkley Point C Site Inspector:

Conclusion of Intervention

The Hinkley Point C Site Inspector concludes that NNB GenCo has demonstrated that it is compliant with LC16: Site plans, designs and specifications. The HPCSI judges NNB GenCo’s performance to be adequate and therefore awards an Intervention Rating of GREEN.