Office for Nuclear Regulation

This website uses non-intrusive cookies to improve your user experience. You can visit our cookie privacy page for more information.

Heysham 2 - LC22 inspection

Executive summary

Purpose of intervention

The purpose of this intervention was to undertake a licence condition (LC) compliance inspection at EDF Energy Nuclear Generation Limited (NGL) Heyham 2 Power Station, in line with the inspection programme contained in the Heysham 2 integrated intervention strategy (IIS) for 2016/17. Specifically, this was part of a fleet-wide, corporate LC22 inspection.

Interventions Carried Out by ONR

As part of this intervention, we inspected NGL's LC22 arrangements for Modification or Experiment on Existing Plant, in accordance with ONR guide NS-INSP-GD-022 Revision 3. We focused on configuration control of plant in the process of being modified. The intervention was based upon a review of associated procedures and interrogation of various lists including Category 1, 2 and 3 lists of modifications, Safety Case Anomalies, Defeat of Interlocks and Long Term Out of Service Plant and interviews with relevant station staff.

Explanation of Judgement if Safety System Not Judged to be Adequate

No safety system inspection was undertaken, hence this is not applicable.

Key Findings, Inspector's Opinions and Reasons for Judgements Made

From our inspection of the arrangements for the control of a modification, focusing on configuration control of plant being modified, we noted sufficient checks and balances within the procedures, electronic modification form and Asset Management System to allow for adequate configuration control.

We sampled how all the open modifications on the station are controlled. This showed that a number of KPIs are monitored, and review meetings are conducted. We did note a number of long standing modifications which appeared to be master or replicant modifications, which were essentially repeat modifications. These made identifying the real longer term active modifications more difficult. We noted that several responsible engineers (RE's) were responsible for a large number of modifications. However, we did consider that the oversight given to active modifications and support to RE's to progress modifications, was over and above NGL's corporate requirements, we considered this to be relevant good practice.

The list of long term out of service plant showed that there was a limited number of long term out of service plant, which indicated that isolations were under control.

The sampled list of safety case anomalies showed that there was a limited number of Interim Justification for continued operation (IJCO) documents; on this basis we considered that there was adequate control of safety case anomalies.

The sampled list of fuel route interlock defeats demonstrated that defeat of interlocks was under control.

Based on our sampled inspection, we judged that the implementation of the arrangements for LC22 reflect relevant good practice and have rated this intervention as Green.

Conclusion of Intervention

Overall, we consider that the arrangements and their associated implementation for LC22 for the sample undertaken met with legal requirements; we have therefore rated this inspection as Green.

There are no findings from this inspection that could significantly undermine nuclear safety nor require a change to the planned interventions and inspections of Heysham 2.