Office for Nuclear Regulation

This website uses non-intrusive cookies to improve your user experience. You can visit our cookie privacy page for more information.

Planned inspection at AWE Burghfield

Executive summary

Purpose of intervention

This report covers planned inspections at the AWE Burghfield Licensed Site undertaken in accordance with ONR’s Integrated Intervention Strategy (IIS) for the Atomic Weapons Establishment Programme.

The inspections undertaken at the Burghfield Licensed Site form part of a series of planned interventions in accordance with the IIS and Integrated Intervention Plan (IIP).

Interventions Carried Out by ONR

The intervention was performed in line with ONR's guidance requirements (as described in our technical inspection guides) in the areas inspected.

ONR conducted a planned inspection and assessment within the Assembly Technology Centre (ATC) of implementation of the Licence Condition (LC) 22 Modification or Experiment on Existing Plant

ONR also conducted interventions by way of update meetings with both the Internal Regulator (IR) and the ATC Facility Head.

Explanation of Judgement if Safety System Not Judged to be Adequate

N/A.

Key Findings, Inspector's Opinions and Reasons for Judgements Made

For the LC 22 inspection, based on the discussions and explanations given, including the sample inspected, on this occasion I am satisfied that there were no shortfalls identified with the implementation of the arrangements for LC22 Modification or Experiment on Existing Plant. Therefore I judged this compliance inspection to have a ‘GREEN’ rating. There were no shortfalls identified in the use of the asset change process, the appropriate categorisation of change, maintenance of the configured baseline and arrangements established to mitigate significant change aggregation. I was also satisfied with regard to my other interventions that there were no shortfalls and no need for any regulatory action at this point.

Conclusion of Intervention

It is ONR’s opinion, that from the sample inspected, the implementation of the established arrangements within the ATC with respect to Licence Condition 22 is to a ‘GREEN’ rating. There are no other findings from this inspection or the other interventions in this report that could significantly undermine nuclear safety.