Office for Nuclear Regulation

This website uses non-intrusive cookies to improve your user experience. You can visit our cookie privacy page for more information.

Various figures on ONR staff numbers and budgets in 2011, 2012, 2013 & 2014

Information requested

Various figures on ONR staff numbers and budgets in 2011, 2012, 2013 & 2014

Information released

Year Total ONR Staff Payroll Budget Overall Budget
2011 411 £31.1m £54.7m
2012 435 £33.9 m £54.3m
2013 454 £35.8m £53.7m
2014 505 £36.5m £62.7m

The fact that payroll increased 2011-13, while the overall budget fell, is due in some part to a reduction in Technical Support Contracts, largely as a result of increased staff numbers and the completion of the first Generic Design Assessment (GDA). We do not retain this data broken down by departments.

Exemptions applied

None

PIT (Public Interest Test) if applicable

None